Project Consultants/Systems Integrators
PRINCE2 Overview The Management Processes.
PRINCE2 is a project management methodology for the organisation, management and control of projects using a process based approach. It comprises eight high level processes. These are:
Directing a project Planning Starting up a project Initiating a project Controlling a stage Managing product delivery Managing stage boundaries Closing a project
Each process is defined with its key inputs and outputs together with the specific objectives to be achieved and activities to be carried out.
Directing a Project
Directing a Project runs from the start-up of the project until its closure. This process is aimed at the Project Board. The Project Board manages by exception, monitors via reports and controls through a number of decision points.
Planning
Planning is a repeatable process, and plays an important role in other processes, the main ones being:
Planning an Initiation Stage Planning a Project Planning a Stage Updating a Project Plan Accepting a Work Package Producing an Exception Plan.
Starting up a Project
This is the first process in PRINCE2. It is a pre-project process, designed to ensure that the pre-requisites for initiating the project are in place. The process expects the existence of a Project Mandate which defines in high level terms the reason for the project and what outcome is sought. The process of starting up a Project should be very short.
Initiating a Project
The objectives of Initiating a Project are to:
Define how the required product quality will be achieved Plan and cost the project Revise the Business Case and confirm it remains valid Ensure the investment of time and effort by the project is justified, taking into account the risks to the project Enable and encourage the Project Board to take ownership of the project and commit to the next stage Provide the baseline for the decision-making processes required during the project's life
Managing Stage Boundaries
This process provides the Project Board with key decision points on whether to continue with the project or not.
The objectives of the process are to:
Assure the Project Board that all deliverables planned in the current Stage Plan have been completed as defined Provide the information needed for the Project Board to assess the continuing viability of the project Provide the Project Board with information needed to approve the current stage's completion and authorise the start of the next stage, together with its delegated tolerance level Record any measurements or lessons which can help later stages of this project and/or other projects.
Controlling a Stage
This process describes the monitoring and control activities of the Project Manager involved in ensuring that a stage stays on course and reacts to unexpected events. The process forms the core of the Project Manager's effort on the project, being the process which handles day-to-day management of the project.
Throughout a stage there will be a cycle consisting of:
Authorising work to be done Gathering progress information about that work Watching for changes Reviewing the situation Reporting Taking any necessary corrective action.
Managing Product Delivery
The objective of this process is to ensure that planned products are created and delivered by:
The Team Manager negotiating details of Work packages with the Project Manager Making certain that work on products allocated to the team is effectively authorised and agreed Ensuring that work conforms to the requirements of interfaces identified in the Work Package Ensuring that the work is done Assessing work progress and forecasts regularly Ensuring that completed products meet quality criteria Obtaining approval for the completed products.
Closing a Project
The purpose of this process is to execute a controlled close to the project. The process covers the Project Manager's work to wrap up the project either at its end or at a premature close. Most of the work is to prepare input to the Project Board to obtain its confirmation that the project may close.
The objectives of Closing a Project are to:
Check the extent to which the objectives or aims set out in the Project Initiation Document (PID) have been met Assess to what extent all expected products have been handed over and accepted by the customer Confirm that maintenance, operation and training arrangements are in place (where appropriate) Make any recommendations for follow-on actions Capture lessons resulting from the project and complete the Lessons Learned Report Prepare an End Project Report Archive the project files Produce a Post-Project Review Plan Prepare a recommendation to the Project Board to notify the host organisation of the intention to disband the project organisation and resources.
|